Amberwell HealthConstruction MOP

How it works

The Method of Performance (MOP)

A MOP tells Amberwell about upcoming construction or maintenance work so the affected areas can prepare. MOPs for all work need at least 48 hours’ advance notice.

  1. The contractor fills out and signs the MOP. Answering Yes to a hazard question asks for the details reviewers need.
  2. Amberwell signs off. The Director of Facilities and the Director of Safety/Security (or their designees) sign every MOP. Infection Prevention also signs when the work needs Class III or IV precautions. Sign-offs happen at the same time.
  3. Any reviewer can send it back with notes. The contractor updates it and signs again, and the sign-offs start over.
  4. When everyone has signed, the contractor gets an email and work may proceed. The printable record shows every signature.

IC matrix: class of precautions

The form works this out from the construction type and the patient risk group.

Patient risk groupType AType BType CType D
Low riskIIIIIIII/IV
Medium riskIIIIIIIV
High riskIIIIII/IVIV
Highest riskIIIII/IVIII/IVIV

Infection Prevention approval is required when the work calls for Class III or Class IV control procedures.